| Overview | Transmission | Power
Systems | Distribution | Wind
Turbine |
 |
PORTFOLIO
 |
 |
PROJECT: West Chester University,
Electrical System Upgrade - Schmidt Residence Hall
LOCATION: West Chester, PA
COMPLETION DATE: January 2005
SERVICES: Electrical Power Systems
OVERVIEW: The project involved the replacement of the building’s 500KVA dry-type unit substation with a new 750KVA transformer and 2000A 120/208VY secondary switchgear.
|
| SYNOPSIS: |
|
The project included the replacement of existing equipment with a new 750KVA dry-type unit substation and 2000Amp secondary switchgear in the electrical service vault. Secondary panels and feeders were replaced for many of the existing loads. In addition, two new secondary panels were located on each floor of the eight floor structure and ultimately allowed for the addition of four new duplex receptacles in each student dormitory rooms. Arris performed all field investigation and developed the bidding document and construction package for the project . Arris is responsible for standard construction administration services on this project.
|
 |
 |
PROJECT: West Chester University,
Electrical System Upgrade - Tyson Hall
LOCATION: West Chester, PA
COMPLETION DATE: January 2005
SERVICES: Electrical Power Systems
OVERVIEW: The project involved the replacement of the building’s 500KVA dry-type unit substation with a new 750KVA transformer and 2000A 120/208VY secondary switchgear. |
| SYNOPSIS: |
Tyson Hall is an eight story student dormitory consisting of three separate wings. New 600A risers were installed in each wing with a 150A 120,208VY 42 circuit panelboard installed on each floor to serve the dorm rooms in that wing. Two circuits with four receptacles were installed in each dorm room. Surface mounted raceway with tamper-proof hardware was utilized to transverse all building interiors.
The majority of work was completed during summer months when the building was not occupied with the transformer and switchgear change-out taking place over the Christmas Holidays. Temporary generator power was provided to power critical building systems during shutdown periods.
Arris completed all design activities and construction administration services for this project. |
 |
 |
PROJECT: West Chester University,
15KV Electrical System Upgrade
LOCATION: West Chester, PA
COMPLETION DATE: October 2005
SERVICES: Electrical Power Systems
OVERVIEW: The project involves the upgrade of the remaining 5KV medium voltage power system on campus to 15KV operation. |
| SYNOPSIS: |
The project includes the replacement of 15 building substations and the installation of an additional 15MVA substation class transformer at the New Street Substation. The substation is served at 34.5KV and requires a new 34.5 KV incoming SF6 switch and the removal of existing lattice structure , transformers and switchgear.
Improvements to the underground distribution system include the installation of approximately 2 miles of new 15 KV feeders to the north and south campus areas. Existing facilities served by the existing 5 KV feeders in the North campus area will be converted to dual 15 kv services. All new services consist of the installation of a new 15 kv SF6 automatic transfer switch and either a new 15 kv dry type transformer or liquid type pad mounted transformer.
Existing facilities being converted consist of many historical buildings including the Old Library, Main Hall and Recitation Hall.
In addition, a new underground duct bank will be constructed through much of the historical “Quad Area” on campus. |
 |
 |
PROJECT: White Haven Center
- Pennsylvania Department of General Services
LOCATION: Foster Township, Luzerne County, PA
COMPLETION DATE: March, 2002
SERVICES: Electrical Power Systems
OVERVIEW: Upgrade of the Electrical Distribution
System.
|
| SYNOPSIS: |
This project consisted of the replacement
of over 6 miles of underground 5KV primary conductors and
approximately 20 medium voltage oil fuse cut-outs. The design
also included the replacement of a number of 5KV automatic
transfer switches in the existing building electrical vaults.
Outage coordination and planning was critical for the operation
to insure continuity of operation to the facility.
|
 |
 |
PROJECT: 5 KV Switchgear Replacement & Distribution
Upgrade - Upper Moreland– Hatboro Sewer Authority Treatment
Plant
LOCATION: Willow Grove, PA
COMPLETION DATE: December 2001
SERVICES: Electrical Power Systems, Environmental
Support Systems
OVERVIEW: System upgrade at the treatment
facility
|
| SYNOPSIS: |
The system upgrade at the treatment facility
includes the design of two sets of double ended 15KV switchgear
and twelve 15KV underground feeders to provide dual service
to each new plant substation. One new building was constructed
to house the one of the switchgear lineups and an existing
switchgear building renovated. Eight 5KV transformers were
replaced with 15KV primary units. The secondary 480/277V switchboards
at each location were upgraded to provide higher amperage services
to each building and process facility.
Load studies were performed at each plant building to identify
the actual demand placed on the system by each particular
load. The load data was compiled and integrated with the
expected future load growth for each building to determine
the proper size transformer to be installed. Each of these
load forms were then integrated to represent the complete
load profile for each building. The project required detailed
planning for all new equipment cutover due to the around
the clock operation of this large wastewater treatment facility.
Downtime windows where as short four minutes at the most
demanding application, the raw sewage pump station.
The system upgrade at the treatment required major construction
around the site of a large around the clock municipal waste
treatment plant.
The environmental processes at the plant require the utmost
in reliability. Protective device coordination studies were
performed to insure all relaying and transfer equipment performed
as specified.
|
 |
 |
PROJECT: West Chester University
LOCATION: West Chester, PA
COMPLETION DATE: N/A
SERVICES: Elecrical Power Systems
OVERVIEW: Upgrade of the existing medium
voltage power system.
|
| SYNOPSIS: |
The project involved transformer capacity increases
at the existing university owned substation, including the
installation of a 15 mva substation class transformer, replacement
of existing antiquated 15 kv switchgear line up, and installation
of a new 34.5 kv incoming SF6 switch.
Improvements to the underground distribution system included
the installation of new 15 kv feeders to the central and
east campus areas. Existing facilities served by the existing
5 kv feeders in the Central/East areas of the campus were
converted to dual 15 kv services. All new services consisted
of installation of a new 15 kv SF6 automatic transfer switch
and either a new 15 kv dry type transformer or liquid type
pad mounted transformer. Existing facilities converted consisted
of five residence halls, performing arts center, parking
garage, student union and the library.
In addition, a new underground duct bank was constructed
to provided medium voltage power service to the current building
projects occurring in the east Campus area.
The project included detailed short circuit calculations
and complete protective device coordination for all new 15
kv feeders, utility services and building services.
The project required detailed planning to transfer the existing
34.5 kv utility feeders, and tntegrate the new eight bay
outdoor 15 kv switchgear. Construction phasing plans were
developed to identify specific tasks for the interim operating
period during which portions of the existing system remained
energized and new systems were commissioned.
|
 |
 |
PROJECT: 69 kv - 23 kv, 20
mva Substation for the Pope and Talbot
LOCATION: Ransom, PA
COMPLETION DATE: December 2001
SERVICES: Electrical Power Systems
OVERVIEW: Design of a new customer owned
69 kv substation at the client’s manufacturing site.
|
| SYNOPSIS: |
The work included the siting of the new substation
in a congested area adjacent to the clients papermill and wastewater
treatment plant.
The scope of the project included the design of dual 69
kv steel poles with davit arm construction. Each incoming
69 kv circuit was dead ended to a structural tower and routed
through a
69 kv air break switch. The load break switches where connected via a
tension bus to 69 kv transformer primary fuses.
The substation class transformers where rated 10/20 mva.
The transformer secondaries utilized aerial cable to metering
PT’s and CT’s mounted on structural towers.
The 23 kv outgoing facility consisted of structural members
supporting post type insulators and aluminum busbar operating
23 kv . The 23 kv busses consisted of operating and transfer
buses. Each 23 kv 1200 A circuit breaker was equipped with
no load disconnects to facilitate removal of circuit breakers
for maintenance.
The project required reconfiguration of the existing 23
kv aerial distribution system to accomadate the abandonment
of the existing utility 23 kv feeders and the integration
of the new substation.
The papermaking operations at the plant require the utmost
in reliability and required a detailed phasing plan for construction
and outage requirements. Protective device coordination studies
were performed to insure all relaying and transfer.
|
|
|
 |
| Portfolio Overview - View
Detailed Portfolio |
| WEST CHESTER UNIVERSITY |
The project involved the replacement of the building’s 500KVA dry-type unit substation with a new 750KVA transformer and 2000A 120/208VY secondary switchgear. |
 |
| WEST CHESTER UNIVERSITY |
The project involves the upgrade of the remaining 5KV medium voltage power system on campus to 15KV operation. |
 |
| WHITE HAVEN - PA DEPT. OF GENERAL SERVICES |
Upgrade
of the Electrical Distribution System. |
 |
| HATBORO SEWER AUTH. TREATMENT PLANT |
System
upgrade at the treatment facility. |
 |
| WEST CHESTER UNIVERSITY |
Upgrade
of the existing medium voltage power system. |
 |
| POPE AND TALBOT |
Design
of a new customer owned 69 kv substation at the client’s manufacturing
site. |
|
 |
NEWS
Arris bidding major Fire Alarm project for the West Chester University in West Chester, Pa. The project includes the replacement of the entire head end system, inter-communication system and twenty seven building systems throughout the campus. In addition, thirty five existing building fire alarm systems will tied into and report all addressable information to the new head end system.
Arris Engineering Group
was recently awarded a professional design services contract to upgrade the electrical and plumbing systems for three major buildings located at the Hollidaysburg Veterans Home Complex near Altoona, Pa. More>>
|
ARC-Flash Analysis
Arris Engineering announces the introduction of ARC Flash Analysis to their list of services. More>>
|
|
 |
|
|